Rockwell Reports 74% Increase In Q1 Carat Production
Vancouver, BC – Rockwell is engaged in the business of operating and developing alluvial diamond deposits, with a goal to become a mid-tier diamond production company. The Company has three existing operations, which it is progressively optimizing, two development projects and a pipeline of earlier stage properties with future development potential.
Rockwell also evaluates merger and acquisition opportunities which have the potential to expand its mineral resources and production profile and would provide accretive value to the Company.
First quarter operational update:
|
Volumes of gravel processed (m3) |
Carats Produced |
|||||
| Q1 2012 | Q1 2013 | % change | Q1 2012 | Q1 2013 | % change | |
| Saxendrift |
325,076 |
453,204 |
39% |
1693 |
2,126 |
26% |
| Saxendrift Bulk X-ray |
- |
- |
- |
- |
1,118 |
100% |
| Tirisano |
- |
123,048 |
100% |
- |
1,222 |
100% |
| Klipdam |
194,192 |
232,216 |
20% |
1,832 |
2,768 |
51% |
| Total |
519,268 |
808,468 |
56% |
3,525 |
6,116 |
105% |
Rockwell Diamonds Inc. announces that volumes of gravel processed in the first quarter increased 56% year on year, with a 74% improvement in carat production from the three operational mines over the same period to 6,116 carats. Overall volumes processed continued to track closer to the Company’s internal targets while budgeted carat recoveries were exceeded as the bulk x-ray proof of concept plant introduced earlier in the year contributed 1,118 carats in the last six weeks of the quarter.
The volume and carat production for the Company’s operational mines for the quarter ended May 31, 2012:
Saxendrift Complex:
- Saxendrift achieved a 39% year-on-year increase in volumes processed to 453,204 m3 for the first quarter, in line with its targets, while carats produced increased 26% to 2,126 carats.
- The bulk x-ray plant was commissioned in April 2012 below budget and on schedule. A total of 1,118 carats were extracted from recovery tailings during the first six weeks of operation of this proof of concept project with the largest stone recovered weighing 74 carats. The next phase of testing is progressing with the processing of additional recovery tailings.
- The in field screen, commissioned in November 2011, increased plant throughput during the first quarter. In addition, it went some way to mitigate the impact of increased sand content of the ore bodies being mined.
- Improving production from Rockwell’s properties that are located adjacent to the Saxendrift Mine is now the Company’s focus. This includes the additional resources acquired as part of the Jasper Project purchase, which became unconditional at the end of May 2012. Plans are also in progress to evaluate the potential of extending mining operations to other parts of the Saxendrift Mine property with the objective of extending the life of this operational footprint.
- The pre feasibility study for Wouterspan, scheduled for completion by the end of 2012 has commenced and is scheduled for completion by year end.
Tirisano:
- Ramp up in production continues, with plant throughput volumes increasing by 30% to 123,048 m3 in the first quarter, from 94,643 m3 in the fourth quarter of fiscal 2012.
- Carat production more than doubled in the three months to May 31, 2012, yielding 1,222 carats compared to 557 carats in the previous three-month period. This was as a result of grade increases to 0.99 carats/100 m3, from 0.59 carats/100 m3 in the quarter ended February 29, 2012.
- Construction of the wet front end facility which has the capability to process gravels with high clay content was completed on schedule at the end of May 2012 and is expected to provide additional flexibility in the mine plan that was previously lacking.
- Maintenance and rationalization of the earthmoving fleet has been a key focus this past quarter.
Klipdam:
- A year on year increase of 20% in plant throughput to 232,216 m3 was due to the conversion to continuous operations, installing a new barrel screen and the removal of five conveyor belts in the front end of the production plant.
- Carat production increased 51% with improved grades as a result of the focus on processing the Rooikoppie gravels. The value per carat was in line with the previous quarter due to current world markets.
- The appointment of a Mine Manager and Mining Manager has significantly improved the overall operation of the mine.
Commenting on Rockwell’s progress in relation to its focus on Diamond Value Management, James Campbell, CEO stated that: “In 2011, our executive management and board put in place two simultaneous strategies for enhancing shareholder value, namely to execute on our plans to optimize production at each of our operational mines and to rebuild the mine life profile of the Company’s assets. The results to date are showing the first positive impacts of these strategies.”
For further information on Rockwell and its operations in South Africa, please contact
James Campbell CEO +27 (0)83 457 3724
Stéphanie Leclercq Investor Relations +27 (0)83 307 7587
Short URL: http://woodlawnpost.com/?p=53442
























